Thomson Reuters – Electrical upgrade
Waveguide completed an electrical and lighting fit-out at Thomson Reuters Dublin offices in 2018
The scope of work broken down into three phases included:
Electrical
Included the supply and installing of the following:
- Containment Systems- 3 compartment containment face fixed to the wall for data and power around the perimeter of office, high-level trunking for data, security, fire alarm, and power.
- General services
- Commando Power Socket for Comms room
- New 3 phase Distribution Board
- Power supplies for external condenser units.
- Spur Outlet for AC (Internal)
- All Data cabling
Lighting Installation
- Supply and Install LED Lighting to all areas
- Full re-wiring of the existing lighting
- Supply and Installation of light switches, dimmer switches and presence detectors throughout
Safety system works
- Supply and Install new fire alarm system with a new panel, smoke/heat detectors, sounders and break glass units inclusive of void detection to suit the new layout
- Supply and Install of emergency lighting.
All work was carried out by our team here at Waveguide to meet clients' requirements in less than 4 weeks.
Details:
Category
Electrical
Location
Ireland

Waveguide completed an electrical and lighting fit-out at Thomson Reuters Dublin offices in 2018
The scope of work broken down into three phases included:
Electrical
Included the supply and installing of the following:
- Containment Systems- 3 compartment containment face fixed to the wall for data and power around the perimeter of office, high-level trunking for data, security, fire alarm, and power.
- General services
- Commando Power Socket for Comms room
- New 3 phase Distribution Board
- Power supplies for external condenser units.
- Spur Outlet for AC (Internal)
- All Data cabling
Lighting Installation
- Supply and Install LED Lighting to all areas
- Full re-wiring of the existing lighting
- Supply and Installation of light switches, dimmer switches and presence detectors throughout
Safety system works
- Supply and Install new fire alarm system with a new panel, smoke/heat detectors, sounders and break glass units inclusive of void detection to suit the new layout
- Supply and Install of emergency lighting.